Yale University

  • Addition of new generator to the infrastructure ‎at Yale’s 4,500 SF West Campus administrative date center
  • The generator project consisted of adding a new ‎‎500 kW backup diesel generator with a 2,000 gallon remote fuel ‎tank and 250 feet of duct bank to protect feeders
  • Commissioning services
  • Other work performed
    • Replacement and upgrade of data center UPS and power feeders