Cambria County Association of the Blind and Handicapped

  • 60,000 SF new addition
  • Conversion of two existing buildings totaling 31,500 SF to manufacturing space and two additions totaling 7,500 SF
  • Project completed in 4 phases:
  • Phase 1
    • Demolish existing two-bay garage and constructing a new two story addition and dock addition
    • Install new chiller and boilers
    • Install new transformer and main distribution gear
    • Install hot & chilled water piping to new addition
    • Install new air handling unit AHU-4 at manufacturing are and tie in utilities
  • Phase 2
    • Provided humidity control
    • Construct new garage addition and first aid room
    • Install new concrete apron at existing garage addition
  • Phase 3
    • Relocate machines and manufacturing to completed areas
  • Phase 4
    • Install new AHU-3 and associated ductwork